21040.8 Preparation of Request for Capital Outlay Projects
-
The COBCP’s are the formal requests for capital outlay projects submitted for approval in the five-year plan. They should be prepared in sufficient detail to describe the type of improvements requested. A COBCP shall include the following information regarding the project:
-
Purpose of the project.
-
Relationship to the Strategic Plan.
-
A discussion of alternatives.
-
The recommended solution and rationale for choosing it.
-
A detailed scope description.
-
The basis or source of the cost information.
-
Description of any impacts to the support budget.
-
Identification of any perceived project risks.
-
A proposed project schedule that identifies start and completion of the various funding phases (i.e., preliminary plans, study, etc.).
-
A detailed cost breakdown.
-
A Management Plan (how will the project be accomplished, swing space, etc.).
-