21040.8 Preparation of Request for Capital Outlay Projects

  • The COBCP’s are the formal requests for capital outlay projects submitted for approval in the five-year plan. They should be prepared in sufficient detail to describe the type of improvements requested. A COBCP shall include the following information regarding the project:

    • Purpose of the project.

    • Relationship to the Strategic Plan.

    • A discussion of alternatives.

    • The recommended solution and rationale for choosing it.

    • A detailed scope description.

    • The basis or source of the cost information.

    • Description of any impacts to the support budget.

    • Identification of any perceived project risks.

    • A proposed project schedule that identifies start and completion of the various funding phases (i.e., preliminary plans, study, etc.).

    • A detailed cost breakdown.

    • A Management Plan (how will the project be accomplished, swing space, etc.).