Article 6 – Regulation and Policy Directives
12010.6.4 Stakeholder Reviews
Revised April 14, 2022-
The RPMBRegulation and Policy Management Branch project manager shall coordinate stakeholder reviews for regulation and policy projects. Requests for stakeholder reviews are sent to the affected programs with a response due date.
-
The program project manager shall specify the level of stakeholder review:
-
Level 1 Priority – One calendar week.
-
This timeframe shall only be used when the department is required to meet external time constraints (e.g., court deadlines, legislative mandates, or the Governor’s executive orders). A justification of such time constraints shall be included in the project submittal.
-
Emergency regulations are always a Level 1 Priority review.
-
-
Level 2 Standard – Two calendar weeks.
-
-