Article 17 – Evaluations and Fiscal Control Audits
22080.9.10 Progress Reviews
-
A progress review of corrective actions shall be scheduled approximately 90 days after approval of the Action Plan by the Director/Chief Deputy Director, unless another interval is appropriate in a unique situation. Progress reviews shall follow the same process as the program compliance evaluation but shall be limited to operations which required corrective action. The approved Action Plan shall be the reference document for the progress review.