44010.3.1 Information Technology Project Reports

  • Two information technology project reports are specified, the Quarterly Project Report (QPR) and the Special Project Report (SPRSpecial Project Reports). These reports:

    • Support continuing communication among all project participants (project management, program management and executive management).

    • Expose potential problems with respect to the availability of resources or the meeting of mandated project dates.

    • Provide for CDC management and control agency review of project progress at appropriate intervals throughout the life of the project.